Skip to main content

Influent Pump Station Project

INFLUENT PUMP STATION PROJECT

The Sewerage Commission - Oroville Region (SC-OR) worked with Jacobs Engineering (formerly CH2M Hill) to design a new influent pump station for the wastewater treatment plant in Oroville.  The new pump station has a designed 15 million gallons-per-day (MGD) pumping capacity, and will include new valves, diversion boxes, flow meter, and Supervisory Control and Data Acquisition (SCADA) control center. 

SC-OR received partial funding from the Water Quality, Supply, and Infrastructure Improvement Act of 2014 for the construction of this project in the amount of $3,776,154.00. Funding was made possible through an agreement with The California State Department of Water Resources and Butte County Department of Water and Resource Conservation. 

On June 15, 2021, SC-OR, along with Jacobs Engineering, held a public bid opening for the influent pump station project.  SC-OR received three bids, and ultimately Gateway Pacific Contractors, Inc. was awarded the project with the low bid of $7,171,451..00.

Project Design Engineer: Jacobs Engineering

Construction Engineers: Coleman Engineering

General Contractor: Gateway Pacific Contractors, Inc.

 

Project Status:

Construction officially began on August 23, 2021.  The PowerPoint slide show displays the project site before construction of the first and second phases of the excavation and shoring. This file is 23 MB.

Construction Progress Sept 2021.pptx

 

November Construction Update: Continuing excavation, building forms for foundations of valve boxes,  bar screen, and metering vault.  . This file is 30 MB.

PIPS Construction November.pptx

 

 December Construction Update: Construction progress was slowed as we received approximately 7 inches of Rain during the month of December.  Work shifting to controlling an pumping ground water.  This file is 14 MB.

December 2021 IPS.pptx

 

January Construction Update: Good weather allowed us to continue construction.  We made significant progress in constructing the foundations of the new wet well the two valve boxes and the bar screen box foundations. This file is 53 MB

January 2022 IPS.pptx

 

 February Construction Update:  Construction of the influent pump station wet well. This file is 20 MB.

February Construction Progress.pptx

 

 March Construction Update: Construction of the the two valve vaults and the flow meter vault. This file is 37 MB.

March Update.pptx